1 General Provisions
1.0.1 This code is prepared with a view to enhance the quality of mineral processing equipment installation engineering of metallurgical concentrator and to guarantee the engineering safety.
1.0.2 This code is applicable to the installation of crushing,grinding and sieving equipment,classifying and sorting equipment,dewatering equipment and feeding and ore drawing equipment of metallurgical concentrator.
1.0.3 In addition to the requirements stipulated in this code,the installation of mineral processing equipment shall also comply with the requirements stipulated in the current relevant standards of the nation.